Mashiva Metals LLP setting up Submerged Arc Furnace in Raigarh
Mashiva Metals LLP proposed Greenfield project for setting up Submerged Arc Furnace of 9 MVA x 2 Nos to produce Silico Manganese 36,000TPA and/ or Ferro Manganese 46,000 TPA and/ or Ferro Silicon 20,000 TPA and/ or Pig iron 63,000 TPA at Plot No. 255, 257(P), OP Jindal Industrial Park, Village- Tumidh, Tehsil- Gharghoda, District- Raigarh (C.G.)
Following facilities are proposed in an area of 2.83 Ha.: 1. Submerged Arc Furnaces (2 Nos.) each with 9MVA input power capacity will be installed for production of Silico Manganese 36,000 TPA and/or Ferro Manganese 46,000 TPA and/or Ferro Silicon 20,000TPA and/or Pig Iron of 63,000TPA.
Total Cost of Project (Including CER) 4527.00 Lakhs.