Monorail receives Commissioner of Rail Safety clearance.
After missing several deadlines, the country�s only monorail corridor is set to make its entire run after it received safety clearance from the Commissioner of Rail Safety (CRS) on Tuesday.
�We have received clearance from the CRS subject to certain conditions. These conditions have to be fulfilled over a period of time. We will now submit our action plan to the government and the operations will begin after we receive the government�s nod,� said Sanjay Khandare, Additional Metropolitan Commissioner, MMRDA.
According to sources the CRS has given clearance to the 19.7-km corridor subject to around 15 conditions. Among them are the availability of sufficient trains, sufficient spares to maintain them, adequate staff and compliance to specifications by the Fire Department.
�Some conditions can be fulfilled immediately while others can be worked on once the operations begin,� added Khandare.
Along with the Phase II (Wadala to Jacob Circle) the MMRDA will also be resuming the Phase I (Chembur to Wadala) services after it was stopped in November after two coaches were gutted in a fire at Mysore Colony station.