NHPC Ltd. commissions Unit 2 of Parbati-II HE project.

NHPC Ltd. commissions Unit 2 of Parbati-II HE project.

NHPC Ltd's Unit # 2 of Parbati-II HE Project (4 x 200 MW) in Himachal Pradesh has been successfully synchronized with the grid at 10-11 MW load at 21:42 Hrs on 22.09.2018. Further, the Load throw off test on Unit#2 has been carried out successfully on 23.09.2018 at 25% load (50MW) between 16:41 Hrs-17:11 Hrs and at 100MW (50% Load) between 19:31Hrs - 19:31Hrs.